Installation Steps
If a spacer was plumbed in prior to the valve installation, loosen all bolts on the spacer and remove from manifold
Position the fully assembled wetware between the Van Stone flanges fixed to the inlet and outlet pipe ends
Ensure that the flow of water matches the directional arrows on the valve body
The flow meter should always be positioned at the inlet of the valve
Rotate the valve to the desired orientation
Ensure that the washers are centered between the flanges
Insert all bolts and hand tighten
Tighten bolts in a star pattern to apply equal pressure across the flange (see drawing below for example). Use a torque wrench set to the torque specified on the pipe-end flange (typically 25 foot pounds for PVC Van Stone flanges)